On August 18, 2025, the Federal Public Procurement Chamber ruled in its decision (Ref.: VK 2–63/25) that scaffolding work constitutes a separate specialist lot and that the overall award of facade and scaffolding work was neither technically nor economically justified in this case.
Our video discussing the judgment:
Facts: The undesirable overall award
The client invited tenders for a total of 19 specialist lots as part of an open tender procedure for the energy-efficient refurbishment of a building complex. The “façade work” lot included not only the demolition and new construction of the external thermal insulation composite system (ETICS), but also the necessary scaffolding work. The specifications explicitly provided for scaffolding erection for third parties (façade and roof trades).
The client justified the combination of the scaffolding and façade work in one lot with the following arguments:
- Technical necessity: The sequential dismantling and construction of the ETICS from top to bottom or from bottom to top requires short-term and constant adjustments to the scaffolding. Only an overall contract award would enable the necessary rapid coordination and manageable procedure that has been practiced thousands of times.
- Economic effects: Close dovetailing would lead to synergy effects and avoid delays caused by the usual long call-off periods (4 to 8 weeks) for external scaffolders. In addition, due to the low contract value for the scaffolding (approx. 1.94% of the total contract value), the separate awarding of contracts should be avoided as an uneconomical splinter lot.
The applicant, a pure scaffolding company, considered this overall award to be inadmissible. It argued that scaffolding work constitutes an independent specialist trade which, according to the HwOuaÜG (Transitional Act on the Occasion of the Second Act Amending the Crafts Code), must in any case be carried out by a scaffolder registered in the Crafts Register — i.e. only by a subcontractor of the façade builder.
Key point of the decision: Coordination costs must not be passed on
The VK Bund ruled in favor of the applicant and found a breach of the requirement to award specialist lots in accordance with Section 97 (4) sentence 2 GWB. The chamber confirmed that scaffolding services constitute a specialist lot due to the independent requirements under craft law (separate training occupation, master craftsman title and collective agreement), which was not disputed in principle by the client.
The chamber rejected the argument of the technical complexity of the façade work. There was no compelling need for an overall award, as according to the client itself, the work had been carried out “thousands of times” and was easy to handle in practical construction terms, which argued against any particular complexity. In addition, there was no technical necessity for an overall award because the scaffolding work had to be carried out by a specialized scaffolder as a subcontractor or bidding consortium anyway due to the provisions of trade law (HwOuaÜG) and the use for other trades (roof). The controllability in the individual lot was given, as the necessary adaptations and conversions could be specifically planned by the specialist planner from the outset (e.g. 10 or 20 conversions per house). The requirements for prompt and immediate implementation could easily be defined as a contractual basis in a separate tender for the scaffolding construction lot and would thus avoid waiting times.
The economic arguments were also rejected by the Chamber. The client’s desire to achieve faster coordination and a common commercial interest and thus avoid obstruction notices, construction time extensions and further remuneration claims did not constitute a permissible economic or technical reason. The legislator made this decision by deliberately accepting the increased coordination effort that arises when dividing the contract into specialist lots in Section 97 (4) GWB and imposing this on the client. Similarly, a split lot argument for supporting services such as scaffolding would be misguided, as these naturally lag behind the main services in terms of value. In addition, scaffolding accounted for 10 to 20 percent of the façade work itself, which argued against the assumption of an uneconomical splinter lot.
As a result, the overall award was inadmissible. The client had to tender the scaffolding services in a separate specialist lot if the intention to procure continued.
Tips for public clients: Stay true to the lots
The ruling underlines that the statutory requirement to award specialist lots is one of the main pillars of public procurement law. The desire for simple coordination or the avoidance of interfaces only justifies an overall award in rare exceptional cases.
- Mandatory separation: As a rule, scaffolding services must always be tendered as a separate specialist lot . Scenarios that justify an exception are hardly conceivable.
- Clear specification: Instead of grouping services together, define the special features of the construction project in the tender documents for the individual lot. If, for example, quick successive retrofits are required, this must be precisely specified in the specifications of the scaffolding lot.
- Coordination effort as a duty: Plan and budget explicitly for the increased coordination effort that arises when awarding lots. This is required by law and must be borne by the client.
- No generalized experience: General references to bad experiences with external scaffolders (“call-off periods of 4 to 8 weeks”) are not sufficient to justify an overall award. The justification must relate to the specific individual case and its particular technical circumstances.
Tips for bidders and funding recipients: Actively report violations of lot bids
For bidders, especially specialized companies (such as scaffolders in this case), the lot splitting requirement is an important protective mechanism that ensures access to public contracts.
- Monitor the market: In tenders, check whether independent specialist trades such as scaffolding, special IT services, cleaning services etc. have been integrated into a larger lot without permission.
- Reason for complaint: If there is a breach of Section 97 (4) GWB because a specialist lot was not tendered separately, this is a clear reason for complaint.
- Check multi-client capability: Consider whether you could offer the separate service if it had been put out to tender separately. The applicant in the present case explicitly confirmed in the proceedings that it can offer and perform the scaffolding services put out to tender in the event of a separate invitation to tender.