In its decision dated March 6, 2026 (case reference: Verg 29/22), the Higher Regional Court of Düsseldorf ruled that the subsequent addition of fast charging infrastructure to concession agreements constitutes a material change that requires a new award procedure. You can find the video of
In its decision dated March 6, 2026 (case reference: Verg 29/22), the Higher Regional Court of Düsseldorf ruled that the subsequent addition of fast charging infrastructure to concession agreements constitutes a material change that requires a new award procedure. You
On May 29, 2024, the Higher Regional Court of Düsseldorf ruled in its decision (Ref.: Verg 35/23) that evaluation systems that assign zero points to the worst bid across the board — regardless of the actual qualitative gap to the
On March 6, 2026, our lawyer Christian Wiere dealt with the decision of the Rhineland Public Procurement Chamber (VK) of June 2, 2025 (Ref.: VK 63/24) in an abante live on public procurement law. The VK Rheinland ruled that a
On December 3, 2025, the Rhineland Public Procurement Chamber (VK) ruled in its decision (Ref.: VK 34/25) that the cumulative requirement of certificates of competence for contractors and managers must be taken at face value — there is no “or”
On June 25, 2025, the Federal Public Procurement Chamber (VK Bund) ruled in its decision (Ref.: VK 1 — 36/25) that the additional request for evaluation-relevant documents in the award procedure is inadmissible and leads to the mandatory exclusion of
On January 10, 2025, the Higher Regional Court of Rostock ruled in its decision (Ref.: 17 Verg 4/24) that the blanket combination of planning and construction services into a total contractor award is inadmissible without sufficient consideration of all relevant
On March 13, 2024, the Higher Regional Court of Rostock ruled (case reference: 2 U 10/23) that a de facto award of a contract below the threshold values can also be stopped by means of an interim injunction if the
On April 23, 2025, the Lower Saxony Public Procurement Chamber (VK) ruled in its decision (Ref.: VgK-10/ 2025) that internal reasons can also justify the annulment of an award procedure. These internal reasons must also be documented in detail in
On December 16, 2025, the Brandenburg Higher Regional Court ruled (case reference: 19 Verg 1/25) that the exclusion of a bidder due to an allegedly unreasonably low offer price is unlawful if the price clarification request is not sufficiently clearly
On October 31, 2025, the Public Procurement Chamber (VK) of Southern Bavaria issued an important decision (Ref.: 3194.Z3-3_01-25–56) on the self-binding nature of public contracting authorities. In essence, it concerned the question of whether a contracting authority may deviate from
On August 18, 2025, the Federal Public Procurement Chamber ruled in its decision (Ref.: VK 2–63/25) that scaffolding work constitutes a separate specialist lot and that the overall award of facade and scaffolding work was neither technically nor economically justified
On January 26, 2024, the Westphalia Chamber of Public Procurement (VK Westfalen) ruled in its decision (Ref.: VK 1–40/23) that the addition of contract values for construction services requires that these are to be viewed as a single structure from
Neue Entscheidungen und Entwicklungen – direkt in Ihr Postfach.
Ob Beschaffung, Nachprüfung oder Zuwendung – wir sagen Ihnen im Erstgespräch, wie belastbar Ihre Ausgangslage ist.
Europe-wide expertise in public procurement law - your competent partner in all phases of the procurement process.
Alternatively, you can send us your application by mail to: abante Rechtsanwälte | Lessingstr. 2, 04109 Leipzig or send an e-mail to: personal@abante.eu