On October 16, 2025, the ECJ ruled in its judgment (Ref.: C- 282/24) that a change in the remuneration method in a framework agreement awarded on the basis of the lowest price award criterion is not automatically to be regarded as a change in the overall nature of the framework agreement. This applies as long as the total contract value changes only slightly and there is no fundamental shift in the economic balance.
Our video discussing the judgment:
Issue: Remuneration adjustment for towing services in Sweden
The decision of the European Court of Justice (ECJ) sheds light on a central question regarding flexibility in public procurement law: To what extent may a contracting authority adjust the contract terms without having to initiate a new procurement procedure?
The initial situation: In 2020, the Swedish police authority (Polismyndigheten) invited tenders for a framework contract for towing services. The only award criterion was the lowest price. The price calculation combined a fixed price for services within an initial radius of 10 km and a variable remuneration per kilometer for distances beyond that. Two framework agreements were concluded on this basis at the beginning of 2021.
The adjustment and its consequences: During 2021, the police authority and the contractors agreed to adjust the remuneration terms retrospectively. The aim was to distribute costs more evenly without increasing the total contract value. The change included an extension of the fixed price radius from 10 km to 50 km and an adjustment of the prices. The police authority stated that the application of this new remuneration model had led to a slight reduction in the total remuneration.
The Swedish Competition Authority (Konkurrensverket) saw this adjustment as an infringement and applied for a fine against the police authority. The court upheld this and sentenced the authority to pay a fine of around 106,650 euros. The changes were to be regarded as substantial and changing the overall character.
Following an appeal, the Swedish Supreme Administrative Court (Högsta förvaltningsdomstol) referred the question to the ECJ as to whether this change in the remuneration modality constitutes a change in the overall character within the meaning of Art. 72 (2) of Directive 2014/24/EU.
Key point of the decision: Clear distinction between “significant change” and “overall character”
The ECJ had to clarify the scope of the term “change in the overall nature” within the meaning of Art. 72 (2) of the Public Procurement Directive 2014/24/EU. This has implications for the application of German law, as there is a corresponding provision in Section 132 (4) GWB.
1. the necessary differentiation
The ECJ ruled that a distinction must be made between a material change and a change to the overall nature of the contract.
Purpose of the flexible regulation: With Art. 72 (2) of the Public Procurement Directive, the Union legislator wanted to provide a far-reaching possibility for simplified amendments below certain value thresholds. This provision serves to ensure a certain degree of flexibility and the possibility for contracting authorities to react pragmatically to circumstances.
Delimitation: If every substantial modification were also to be regarded as a change in the overall nature of the contract, Art. 72 (2) of the Public Procurement Directive would be practically ineffective. The term “overall nature” only covers the most important material changes that entail a fundamental change in the subject matter or nature of the contract or a fundamental shift in the balance.
2. the valuation of the change in remuneration
A simple change to the remuneration method — such as a shift in the ratio of fixed to variable remuneration — does not in itself constitute a fundamental change to the subject matter of the framework agreement.
The crucial point is that a change in the remuneration method that leads to a minor change in the overall value does not in any case mean a fundamental change in the subject matter or nature of the framework agreement.
Exception in the case of upheaval: Only in exceptional circumstances, such as a drastic change in the ratio between fixed and variable remuneration, can such an adjustment lead to a fundamental shift in the balance and thus to a change in the overall character. This must be examined if the change causes a complete upheaval in the system and puts the award recipient in a significantly more favorable position.
Tips for public clients: pragmatic solutions with legal certainty
The ruling underlines that a pragmatic, solution-oriented approach to public procurement law must always go hand in hand with professional excellence and transparency.
- Use of the scope for flexibility: The value limits in Art. 72 Para. 2 of the Public Procurement Directive (10% for services, 15% for works contracts) provide a clear framework for necessary adjustments limited in value as long as the overall character is not changed.
- Documentation of the balance: Complete documentation is key to legal certainty. Whenever the remuneration method is adjusted, it must be possible to prove that the change does not cause a fundamental shift in the economic balance.
- Examination in the event of a change of system: Caution is required if the change of remuneration modality represents a complete upheaval of the system of the original contract, as this may constitute a change in the overall character of the contract.
Tips for bidders and applicants: Protect your rights to fair competition
As a bidder, you are entitled to expect that the competition will be fair and transparent and that subsequent changes will not undermine the original procedure.
- Focus on the economic balance: In the event of known contract amendments, check not only the value limits, but also whether the economic balance has been fundamentally shifted in favor of the contractor.
- Critically scrutinize remuneration methods: If a client makes a far-reaching shift from fixed to variable costs or vice versa, this can have a significant impact on the bidder group and the bid calculation.
- Ensure legal protection: The procedure serves to ensure compliance with the principles of equal treatment and transparency. Effective legal protection before the public procurement tribunals and higher regional courts applies to the upper threshold range.