On April 28, 2025, the Federal Chamber of Public Procurement (VK) ruled in its decision(Ref.: VK 2–27/25) that an overall award instead of a specialist lot award is permissible if there are technical reasons that make it necessary to integrate all service steps in one hand in order to achieve the desired level of quality. The case in question involved the award of a general contractor contract for the construction of a new bridge with a temporary bypass.
Our video discussing the judgment:
Facts: New bridge construction, narrow construction area and required optimization
The specific case concerned an open procedure for the replacement construction of a bridge including the construction of a temporary bypass. The contracting authority put the project out to tender as an overall award to a general contractor (GC). The services to be provided comprised a large number of individual services, including demolition and dismantling work, special civil engineering, earthworks and excavation work as well as the relocation of pipelines.
The award criteria were: Price (70 %) and the design of the construction process with possible optimizations (30 %).
One bidder objected to the lack of lot formation, as the demolition work, special civil engineering and earthworks each constituted separate specialist lots and could be awarded separately. After the Ag did not remedy the complaint, the bidder filed an application for review with the VK Bund.
The client’s reasons for awarding the contract as a whole included the close interlinking of the trades, the inefficiency of awarding the contract in lots (reference to the construction phase plans), the warranty issues and the predicted extension of the construction period if lots were formed. In addition, coordination with the production cycles of a neighboring electrical steelworks was essential due to the required blocking periods and required very tight timing of all construction work.
Key point of the decision: When technical reasons justify the overall award
The application for review was rejected as unfounded. The VK Bund confirmed the legality of the overall award.
1. principle of lot allocation vs. exceptional case
The statutory principle in Section 97 (4) sentence 2 GWB (or Section 5 (2) no. 1 sentence 2 VOB/A EU) provides for services to be awarded in partial lots (quantity) and specialist lots (type or specialist area). The Chamber confirmed that there are separate markets for the services in dispute, such as earthworks and specialist civil engineering work as well as demolition, and that there are therefore specialist lots.
However, the exception of Section 97 (4) sentence 3 GWB (or Section 5 (2) no. 1 sentence 3 VOB/A EU) applies, according to which an overall award is permissible if economic or technical reasons make this necessary.
2. weighting of the technical reasons
The VK Bund found that the technical reasons predominated in this individual case. Technical reasons therefore exist if:
- They make it necessary to integrate all service steps under one roof in order to achieve the level of quality aimed for by the client.
- In the case of separate tenders, there is a risk of receiving partial services which, although individually compliant with the tender, do not fit together as a whole and therefore do not meet the procurement requirements in the desired quality.
3. the arguments for the overall award
The VK Bund essentially based its decision on the following aspects, which together justified the exception:
- Close technical and temporal integration of the trades: Due to the complexity of building a new bridge, the construction work could not be carried out successively one after the other, but had to be carried out in parallel and recurrently in several construction phases. The trades are interlinked (e.g. demolition only after structural safety/concrete reinforcement), which requires special measures from a single source.
- Coordination effort and time flexibility: The overall award to a general contractor ensures optimal coordination of the repetitive trades on the spatially limited construction site. If lots were awarded, the agent would have to specify exact execution deadlines for each lot, which would have prevented the necessary flexibility in the case of such a complex and dynamic construction process. The estimated extension of the construction period of up to two years if lots were divided up was accepted as a weighty argument.
- Consideration of the quality criterion: The award criterion of designing the construction process with optimization proposals only makes sense in the case of an overall award. The required optimization refers precisely to the interaction of all trades and services. The procurement autonomy of the public authority to make use of the expertise of the specialist companies to optimize the overall project would be curtailed if lots were awarded.
- Public interest: The risk of collapse of the existing bridge and the associated high public interest in removing the source of danger as quickly as possible flank the technical reasons.
Tips for public clients
The decision is an important confirmation of the possibility of the overall award, but sets high standards for the justification.
- Document comprehensive consideration: When deciding against awarding a lot, you must always weigh up and document the conflicting interests comprehensively. It is not enough if the reasons are worthy of recognition — they must prevail. List at least one anchor point in the award notice, which can be supplemented by subsequent reasons in the review procedure.
- Focus on technical interlinking: Concentrate on arguments that demonstrate an indispensable technical and/or temporal interlinking of the trades. This is particularly relevant for complex infrastructure projects in which trades interlock or are repeated several times.
- Use quality and optimization: Include objectifiable quality levels and the possibility of optimization of the overall project by the bidder as an award criterion in the tender documents. This strengthens the argument that the desired procurement requirements can only be met through responsibility from a single source.
Tips for bidders and funding recipients
As a bidder or grant recipient, you should not reject an overall award as being contrary to procurement law.
- Checking the procurement requirements: Check carefully whether the quality or optimization required by the client can actually only be achieved through an overall award. The general coordination effort or warranty interfaces alone are generally not sufficient justification for an overall award.
- Concrete lot argumentation: If you submit a complaint, argue specifically for the lots you are seeking and explain why the alleged technical interdependencies do not prevent separability.
- Use the concept: In the case of overall awards with the award criterion “concept/construction process”, bidders should make maximum use of their expertise in optimizing the construction process in order to gain a competitive advantage.
abante Rechtsanwälte provides ongoing support to public clients and bidders in complex construction and planning procurement law. We will be happy to provide you with a concrete assessment of the lot formation in your project.