Comment on Higher Regional Court of Celle, judgment of November 20th, 2019, 14 U 191/13
Facts of the case
The plaintiff applied for the contract for road construction work. Soil and rock had to be removed from the excavation area and disposed of. The plaintiff is now claiming additional costs from a supplement because a different soil quality was found during the execution of the work than that specified in the award documents.
As is so often the case, the starting point was a contradictory performance specification. In the construction description, it was stated with regard to the soil properties and geological conditions that the existing soils could not be assigned to any particular installation class in accordance with LAGA M 20 (Code of Practice 20 of the German Waste Management Association). Accordingly, the defendant public contractor did not make any classification in the regulatory part of the bill of quantities. It also stated: “soil not requiring monitoring”. In contrast, the likewise enclosed expert opinion proposed to treat “the soil analogous to the installation class Z 1.1 of the recommendations of the LAGA”. In addition, there were conspicuously high heavy metal contents in the eluate.
When the later contractor or plaintiff (at that time still a mere participant in the awarding process) pointed out that the expert opinion and the specifications did not match, the client amended the specifications. Namely, he classified the soils to be solved and recycled in the regulating part of the specifications, which he amended quickly before the submission, in LAGA Z.1.1. It also now said: “Soil requiring special monitoring”. Furthermore, the soils were to be “disposed of”.
After receiving the order, the plaintiff contacted an expert office directly and had the soils examined. The new expert opinion came to the conclusion that two mixed soil samples were to be assigned to an installation class >Z 2 and one mixed soil sample to installation class Z.1.2 of the LAGA recommendations.
This was the beginning of the dispute. The later plaintiff claimed additional costs, which the client rejected. The plaintiff then filed a claim for obstruction, which was also rejected by the client, who was later the defendant.
A few months later, the mine operator refused to accept the delivered excavated soils. The soils fell under the LAGA Z.1.2. installation class; this was the result of a further expert opinion, this time probably obtained by the mine operator.
The plaintiff then again reported concerns, obstruction and additional costs to the defendant client. It was then agreed to obtain a joint expert opinion. This came to the conclusion that the recycling could take place in the sand pit of the mine operator. This was actually good news for the defendant client. But, of course, this did not meet with much approval from the plaintiff, who — with a new expert opinion — continued to reject the installation in the pit.
In fact, installation in the pit occurred to the extent of 89%. The installation is said to have been treated differently in part on site, which is said to have caused additional costs. A considerable part was installed elsewhere; the client paid for this separately.
Legal Appraisal
The court rejected the claims for reimbursement of additional costs and damages. The plaintiff was right insofar as the classification in installation class LAGA Z.1.1 had been wrong. However, the relevant item in the bill of quantities had been recognizably incorrect. In this case, the plaintiff had violated its duty to check and point out. It could not claim any trust worthy of protection.
The court derives the recognizable defectiveness of the bill of quantities from several circumstances. First, it emphasizes the general principles. In the interpretation of the building specification, the wording, the special circumstances of the individual case, the custom of the trade and the principles of good faith are to be taken into account. Pursuant to Sections 133, 157 of the German Civil Code (BGB), the interpretation must always be made according to the objective horizon of the potential bidders. It is true that in the specifications a classification according to LAGA Z.1.1. is expressly made — in the opinion of the court expert: incorrectly. However, this alone was not important: The rest of the item text and the other tender documents had to be taken into account just as much as the history, i.e. how this classification had come about in the regulating part of the bill of quantities. Thus the changed position text contained references (e.g. “particularly in need of supervision”), which could not be classified legally beyond doubt, but which had to be interpreted as a warning. Furthermore, the word “dispose of” in the amended version of the bill of quantities indicated, according to the general understanding of the language, that it was about recyclable soils in the sense of LAGA Z.1.2 — and precisely not about cases of LAGA Z.1.1. In addition, according to the OLG, the amendment of the bill of quantities that took place shortly before the submission was based precisely on a request by the plaintiff. The plaintiff had ultimately brought about the changes in the wording itself and must have recognized them accordingly. Furthermore, the classification according to LAGA Z.1.1. could not be reconciled with the expert opinion which had been attached to the bill of quantities and which itself explained why such a classification was not possible. Translated with www.DeepL.com/Translator (free version)
The court derives the recognizable defectiveness of the bill of quantities from several circumstances. First, it emphasizes the general principles. In the interpretation of the building specification, the wording, the special circumstances of the individual case, the custom of the trade and the principles of good faith are to be taken into account. Pursuant to Sections 133, 157 of the German Civil Code (BGB), the interpretation must always be made according to the objective horizon of the potential bidders. It is true that in the specifications a classification according to LAGA Z.1.1. is expressly made — in the opinion of the court expert: incorrectly. However, this alone was not important: The rest of the item text and the other tender documents had to be taken into account just as much as the history, i.e. how this classification had come about in the regulating part of the bill of quantities. Thus the changed position text contained references (e.g. “particularly in need of supervision”), which could not be classified legally beyond doubt, but which had to be interpreted as a warning. Furthermore, the word “dispose of” in the amended version of the bill of quantities indicated, according to the general understanding of the language, that it was about recyclable soils in the sense of LAGA Z.1.2 — and precisely not about cases of LAGA Z.1.1. In addition, according to the Higher Regional Court, the amendment of the bill of quantities that took place shortly before the submission was based precisely on a request by the plaintiff. The plaintiff had ultimately brought about the changes in the wording itself and must have recognized them accordingly. Furthermore, the classification according to LAGA Z.1.1. could not be reconciled with the expert opinion which had been attached to the bill of quantities and which itself explained why such a classification was not possible. Translated with www.DeepL.com/Translator (free version)
“However, the plaintiff was not allowed to calculate with a soil according to LAGA Z 1.1 without clarification, since already from the expert opinion of I. Ingenieurgesellschaft mbH of 09.04.2009 — which was also taken note of by the plaintiff — and the aforementioned notes in the construction description and in the specifications, it results otherwise, as stated.”
Without further ado, the Higher Regional Court of Celle concluded that claims for additional compensation should be ruled out. This was because the geological conditions found and those tendered did not differ at all. Nor could the plaintiff have relied on the fact that the soils complied with LAGA Z.1.1. Ultimately, for the same reason, claims for “culpa in contrahendo due to faulty tendering” failed, as the Higher Regional Court of Celle describes it. The plaintiff had a “duty to check and inform” and could not “claim any disappointed trust worthy of protection”.
The Higher Regional Court now gives legal reasons why this must be the case from its point of view. It is true that in principle there is no obligation on the part of the bidder at the tender and offer stage to point out errors contained in the specifications. However, the principle of the requirement for correct conduct in contract negotiations implies an obligation on the part of the contractor to check and point out errors if the contract documents are obviously incorrect. Thus, the contractor may not simply accept a list of services which is obviously incomplete or incorrect. He must clarify any doubts arising from this before submitting his bid and, in particular, obtain sufficient information about the intended construction method (type and scope). If the contractor fails to provide the required information in such a case, he is prevented from making additional claims in accordance with the principle of good faith.
The plaintiff was also aware of its duty to check and inform, since it had asked. Precisely because the applicant had inquired, it was obliged to carry out a particularly thorough examination. The fact that the plaintiff had doubts about the classification is also shown by the fact that it commissioned a soil expertise immediately after the award of the contract. At the same time, the defendant could not be said to have acted in bad faith. It had wanted to remedy the situation, so it could not be accused of a deliberately incorrect invitation to tender.
Conclusion
If one asks what was the bidder’s undoing, it is still a little too early. It is not yet clear whether and how the BGH will take a position. However, a few interesting observations can be made:
The Higher Regional Court of Celle recognizes an obligation on the part of the bidder and subsequent contractor to provide information and carry out checks, even during the award procedure prior to submission of the bid. If he violates this, the Higher Regional Court wants to cut off “additional claims”. I.e., supplements.
The Higher Regional Court of Celle recognizes an obligation to provide information in the case of recognizable errors. The Celle Higher Regional Court affirms recognizability in the case of obvious errors or obvious gaps in the specifications.
It is not entirely clear whether the Higher Regional Court applies a subjective or an objective standard for the obviousness or recognizability. On the one hand, it argues very individually. The bidder had already inquired during the award procedure, and had also commissioned an expert opinion immediately after the contract was awarded. This proves his “doubts”. On the other hand, normative considerations are also mentioned.
Against this background, the decision of the Celle Higher Regional Court is ambivalent from the bidder’s point of view. It can be interpreted as an appeal for maximum restraint; whereby this view is associated with considerable risks if the case law falls back on a mixed, objective-subjective standard and/or even the early submission of supplementary offers, which even the bidder who remains silent in the award procedure will hardly be able to avoid, is regarded as sufficient evidence. The decision could therefore also be seen as an incentive to speak up in the award procedure.
One thing the decision is certainly not: an outlier or an isolated case. It is the third decision of the Celle Higher Regional Court, with which the bidder and later contractor is to be assigned more responsibility in the award procedure (see Celle Higher Regional Court, judgment of 02.10.2019, 14 U 171 / 18; Celle Higher Regional Court, judgment of 31 January 2017, 14 U 200/15). This may indicate a paradigm shift.
*This legal tip is not a substitute for legal advice in individual cases. By its very nature, it is incomplete, nor is it specific to your case, and it also represents a snapshot in time, as legal principles and case law change over time. It cannot and does not cover all conceivable constellations, serves entertainment and initial orientation purposes and is intended to motivate you to clarify legal issues at an early stage, but not to discourage you from doing so.